Mining Multinational Adani Avowed Self-Funding for Coal Mine in Galilee Basin

Mining Multinational Adani Avowed Self-Funding for Coal Mine in Galilee Basin

Closed
by December 4, 2018 Biz, Business, Mining

Having been returned empty-handed by the 30 domestic and international banks and international banks and lenders for funds, Adani Groups has resolved to finance a comparatively smaller coal mine at the basin of Galilee, all by its own.

The scaling down of the project has been extensive. Adani Mining chief executive Lucas Dow said the mine will cost A$2 billion and initially produce up to 15 million tonnes of thermal coal per year, with plans to ramp production up to 27.5 million tonnes per year.

Federal Resources Minister Matt Canavan has described Adani as a “little Aussie battler” and praised the newly scaled-down project’s purported regional economic benefits.

That is far more modest than the A$16.5 billion investment in digging up 60 million tonnes of coal a year which the company first announced in 2010. The original plan was to transport the coal along a new 388km rail line to a specially built terminal at Adani’s Abbot Point coal port, for export to India. Under the scaled-down version of the project, Adani will need to secure access to existing rail infrastructure.

But there is still no guarantee that the mine will necessarily go ahead. Opening a new coal mine – even one with a relatively modest A$2 billion price tag – is socially and environmentally irresponsible, given the urgency with which the Intergovernmental Panel on Climate Change says we need to reduce global greenhouse emissions, the fact that Australia is not currently on track to meet its own emissions targets, and of course the fact that 2018 is on course to become the fourth-hottest year on record.

The economics barely stack up either. A recent IEEFA report indicated that coal is facing a terminal decline as Asian markets make the transition to cheaper and more efficient renewable alternatives. Existing thermal coal power in India costs US$60-80 per megawatt-hour, roughly double the cost of new renewable generation. The Mundra coal plant, where much of the Adani coal was destined, is already operating under capacity and has been closed for significant periods.

Adani has decided not to proceed with its initially planned 388km rail link, and will instead aim to use the existing Aurizon rail infrastructure. However, there is a 200km gap in this link which will cost a significant amount to bridge – albeit almost certainly much less than the A$2.3 billion cost of the originally planned railway. Aurizon Network is legally obliged to consider Adani’s access application but has not yet assessed and approved it.